By late July, D.B. Wood Road between SH 29 and Oak Ridge Road had all four lanes open. That ended years of work on a stretch the City funded through its 2015 road bond. Twelve weeks later, on October 19, crews set up one segment farther north. TxDOT's SH 29 West project was already underway by then, and its first work zone starts at River Chase Boulevard.
The two projects keep opposite hours. SH 29 closes lanes overnight and D.B. Wood closes them in daylight. Both are scheduled to run into the second half of 2027, so for River Chase the clock on the dashboard decides which work zone a trip will run into.
D.B. Wood's Finished Stretch Had About Twelve Weeks
Phase I covered D.B. Wood from SH 29 to Oak Ridge Road. The City's project page puts the full remaining cost of that segment at about $26.4 million. It also reports all four lanes open by July 27, 2026, and the contractor, Jordan Foster, packed up and left by August 24.
Jordan Foster won the next contract too. City Council approved Phase II Part A, which runs from Oak Ridge Road to just north of Cedar Breaks Road, with the same firm that had just finished Phase I. The council award describes about 0.75 mile of two-lane collector road. It will be widened into a four-lane divided roadway with sidewalks, culverts, drainage, lighting, signs and pavement markings. The contract includes three left-turn lanes and conduit for future traffic signals.
The work started with traffic barriers and rolling lane closures. In early November that turned into alternating one-way traffic with flaggers between Oak Ridge Road and Cedar Breaks Road, from 7 a.m. to 6 p.m. on weekdays.
This segment is the middle piece of a longer plan. The City's D.B. Wood Phase II project page describes widening 2.3 miles to four lanes with a median and a shared-use path, all the way to the Public Safety Operations and Training Center near Williams Drive. Part B, from Cedar Breaks Road north, was in federal permitting review as of the July council memo and was expected to go out for bid in early 2027.
SH 29's Work Zone Begins at River Chase Boulevard
The SH 29 West project covers the highway from Wolf Ranch Parkway to I-35. TxDOT runs the construction, and the City and TxDOT split the bill. TxDOT paid for design, and the City set aside $9.5 million in Georgetown Transportation Enhancement Corporation funds for construction. Dan Williams Company came in as low bidder at $7,574,102 and held its pre-construction meeting August 13.
Phase 1 takes place in the middle of the road. According to the City's SH 29 West project page, crews are closing center lanes and medians from River Chase Boulevard to the I-35 service road. They are tearing out the old striping, median and asphalt, then laying new pavement, curbing and striping for an added third lane. The October 21 update said the median closures were continuing for added turn lanes, with occasional night work closing one eastbound and one westbound lane.
The SH 29 and D.B. Wood intersection has been rebuilt once already. In 2023, Community Impact reported the completion of a separate project there. That work added east and westbound turn lanes and a raised median on SH 29, plus two southbound left-turn lanes and a raised median on D.B. Wood. The project now underway is a separate package that covers the length of the corridor.
Two Projects, Two Clocks
The November closure listings show the pattern clearly. Each project keeps its lane closures to a different part of the day.
| SH 29 West | D.B. Wood Phase II Part A | |
|---|---|---|
| Work zone | River Chase Blvd to I-35 frontage road | Oak Ridge Rd to Cedar Breaks Rd |
| November closure type | Inside lanes closed, both directions | Alternating one-way traffic with flaggers |
| November closure hours | 8 p.m. to 5 a.m. | 7 a.m. to 6 p.m. |
| Listed November dates | Nov. 1–6 and Nov. 8–13 | Nov. 2–6 and Nov. 9–13, weekdays |
| Contractor | Dan Williams Company, for TxDOT | Jordan Foster, for the City |
| Anticipated completion | Aug. 12, 2027 | Oct. 21, 2027 |
Those specific windows ended November 13. The City posts new ones on its Street and Lane Closures page, which carried a November 4 update with both projects listed together. Check that page before a trip. Each project page also has a "Subscribe to Project Updates" option.
How the Split Plays Out, Trip by Trip
The day-and-night split means each common trip from River Chase meets these projects in a predictable way.
- A weekday morning drive east toward I-35. SH 29's November closures ended at 5 a.m., so the morning commute ran through a highway with its center under construction but its inside lanes open. Watch for the median work, which continues during the day under the October 21 update.
- A late return on SH 29. Anyone coming home from I-35 after 8 p.m. on a listed closure night drove the whole stretch to River Chase Boulevard with the inside lane closed in their direction.
- A weekday drive north on D.B. Wood. From SH 29 to Oak Ridge Road, the new four-lane Phase I section is finished. Past Oak Ridge, between 7 a.m. and 6 p.m., the road narrows to one lane with flaggers taking turns.
- A Saturday morning at Cedar Breaks Park. The U.S. Army Corps of Engineers' directions to Lake Georgetown send drivers from SH 29 to D.B. Wood, then onto Cedar Breaks Road for about 1.5 miles to the park. That puts every trip to Cedar Breaks through the Part A work zone. The November flagger windows were all weekday daytime hours, so a weekend outing skipped them.
- An evening walk at Overlook Park. Overlook Park is the other Lake Georgetown park the Corps routes through D.B. Wood, by way of Lake Overlook Drive. After 6 p.m., D.B. Wood's flaggers had cleared out on the listed days, and SH 29's night closures stayed on the highway east of River Chase Boulevard.
What Waits at the End of the D.B. Wood Route
Cedar Breaks Park sits at 2100 Cedar Breaks Rd on Lake Georgetown. Recreation.gov lists the day-use area as open daily from 6 a.m. to sunset and notes the park's access to the Goodwater Loop Hiking Trail. Visitors need a vehicle pass, which costs $5 for one day or $40 for a 12-month USACE pass. If you visit more than eight times a year, the annual pass costs less than buying day passes, and it takes care of the gate on mornings when the drive in already includes a flagger stop.
Not every trip has to leave the neighborhood. The River Chase HOA lists a clubhouse, pool and tennis courts among its community amenities.
Two End Dates, Ten Weeks Apart
SH 29 West is scheduled to finish first, with anticipated final completion on August 12, 2027. D.B. Wood Phase II Part A follows on October 21, 2027. Both dates are projections, and either can move.
When both finish, the drive from River Chase Boulevard will look different in both directions. SH 29 will have a third lane and new turn lanes all the way to I-35. D.B. Wood will be four lanes from SH 29 to just past Cedar Breaks Road, and the new segment adds a divided roadway, sidewalks, turn lanes and conduit for future signals. Part B, the segment north of Cedar Breaks Road toward Williams Drive, was expected to go out for bid in early 2027.
If you're curious how the SH 29 and D.B. Wood improvements might affect your River Chase home's value, Marion Lamantia is glad to go through it with you, street by street. Start with a free home valuation, or browse her River Chase neighborhood guide.